Skip to main content
This work is funded by people like you. Donate ↗

Martin K. Eby Construction Co. v. Dallas Area Rapid Transit

369 F.3d 464 (5th Cir. 2004)

Court: Fifth Circuit
Decided: April 29, 2004
Docket: 03-10728

Holding

A contractor must exhaust administrative remedies established by a regional transportation authority's procurement regulations and incorporated into the parties' contract before filing a breach-of-contract action in court.

What This Case Is About

Martin K. Eby Construction Company contracted with DART to build a section of Dallas’s light-rail system. When Eby encountered allegedly deficient bid specifications, it sued DART in federal court for breach of contract and misrepresentation. The Fifth Circuit affirmed dismissal, holding that Eby must first exhaust DART’s administrative dispute-resolution process before seeking judicial relief.

The Facts

In April 2002, DART awarded Eby a contract to build a section of DART’s light-rail line near downtown Dallas. During the first six months, Eby made little progress, which it attributed to numerous deficiencies and inaccuracies in DART’s bid designs. DART blamed Eby.

DART’s bid solicitation — incorporated into the contract — required bidders to “exhaust administrative remedies” before seeking judicial relief. DART’s procurement regulations, authorized by Texas statute, established an administrative dispute-resolution process including submission to a contracting officer, administrative appeal before hearing officers (mostly current or former members of the Armed Services Board of Contract Appeals), and quasi-judicial proceedings with discovery and representation by counsel. DART’s contract contained a parallel disputes clause. Eby never submitted its claims to this process and instead filed suit in federal court.

What the Court Decided

The Fifth Circuit affirmed dismissal under Rule 12(b)(6). The court held that Texas law generally requires parties to exhaust administrative remedies before seeking judicial review of government entity decisions. Here, two independent grounds supported exhaustion: (1) the Texas Legislature delegated to DART the authority to “adopt and enforce” dispute-resolution procedures, and (2) Eby contractually agreed to submit disputes to DART’s administrative process.

The court rejected Eby’s arguments that governmental immunity (or its absence) eliminated the exhaustion requirement, and that alleging material breach excused performance of the exhaustion obligation. The court also held that Eby’s misrepresentation claim was really a subset of its breach-of-contract claim and was similarly subject to exhaustion.

Why This Case Matters for Your § 1983 Case

Although Martin K. Eby is a government contract case, the exhaustion of remedies principles it discusses are relevant to § 1983 litigation:

Key Takeaway

When a government contract or enabling statute establishes an administrative dispute-resolution process, a contractor must exhaust that process before filing suit — and the exhaustion of remedies doctrine applies regardless of whether the government entity enjoys immunity, though § 1983 constitutional claims generally do not require exhaustion of state administrative remedies.

Have corrections or want to suggest a change? Let us know ↗